Artificial intelligence does not drink water. The cooling towers that cool data centers evaporate it. A large 200 MW data center evaporates about 8,600 m³ of water a day — as much as a city of 60,000 people uses. And it takes that water from the same wells and rivers as the city.
Scientists in Texas have published a study: desalination of underground water can cover the cooling needs of data centers. They introduced a metric called “saline water use intensity” and built a program for the officials who issue permits. It looks like a search for a solution, but in fact it is technical illiteracy and helplessness.
Look at the choice on offer. The program has 2 ways of desalination: the membrane (reverse osmosis, RO) and evaporation — boil the water, condense the steam, and collect the fresh water.
A membrane works only with seawater, and does that poorly: a lot of energy, a lot of chemicals, more than half of the water goes into brine, and there is nowhere to dump it except the sea, which it kills. Osmotic pressure rises with salinity, and at about 7% (70 g/L) the pump can no longer push water through the membrane. Underground water has a salinity of 10–20%, so membranes are not applicable here. The officials in Texas seem to have arrived from Mars.
Evaporation copes with any brine: bring the water to a boil, catch the steam, and condense it. But heating takes 100–250 kWh per m³, and at $0.12 per kWh that is $12–30 per m³. On top of that, the walls scale up: calcium carbonate and sulfate settle on a hot wall faster the hotter it is. The heat exchanger clogs, the plant stops for cleaning, chemicals go by the bag.
Now the main point. The “gentlest” scenario of the study — the Longview project — proposes treating underground saline water with two-stage osmosis: water that has passed the first membrane is run through a second. But seawater with 3.5% salinity yields only 40–50% fresh water; the rest is brine at 6–7%, which is the limit of a membrane, and a second pass cannot desalinate it: physics says so, and you cannot give physics orders. On top of that, RO already costs more than $2 per m³, a double pass doubles the cost, and the brine is again to be pushed underground. The sea is not available everywhere for dumping. And dumping into the sea is fine — nobody pities it! In my view, this is a crime.
The Permian Basin Holds the Water the Data Centers Need
The idea is understandable: not all data centers stand by the sea, so water can be taken from the oilmen. The Permian Basin yields more than 20 mln barrels of produced water a day — over 3 mln m³. Its salinity is 10–20% and more, 3–6 times higher than seawater, and it contains traces of oil, benzene, boron, iron, and radioactive radium.
Today this water is trucked and piped for hundreds of kilometers to be injected underground under pressure. There is a catch: West Texas now shakes badly after injection, earthquakes have become routine, and the regulator is already limiting injection.
The picture is almost an anecdote: data centers lack water, while oilmen are drowning in water and pay to inject it underground. Between them, 2 desalination options are being wedged in, but a membrane will not take the brine in 1 pass or in 10, and evaporation makes the water golden.
In September 2026 the Texas governor suspended new permits for data centers. While officials invent options, construction stands still and brine keeps being pushed underground.
Brine Can Be Desalinated Without Boiling and Without a Membrane
The universal solution is Arbok Evaporation. Water boils in a vacuum reactor without heating and evaporates at ambient temperature, even at +5 °C (41 °F). There are no membranes, no reagents, no filters, no calcium scale in the pipes. The technology works with brine of any strength, up to 35% — the Dead Sea level — at an energy consumption of 0.72 kWh per 1 m³. For comparison: seawater osmosis uses 4–8 kWh/m³, evaporation 100–250 kWh/m³ in electricity equivalent.
Climbers know this effect: on the summit of Everest, water in a kettle boils at only 70 °C. The boiling point depends on pressure, and Arbok has taken this effect to the point where water evaporates from brine in a matter of minutes at room temperature.
There is no hot wall, so scale has nothing to grow on. The trouble that kills thermal plants does not occur at Arbok. The salt is separated in dry form, with 10–15% moisture, and goes straight into big bags. The same process recovers lithium, magnesium, other salts, heavy metals, and REE from it.
For One 200 MW Data Center the Energy Need Is 139–347 Times Lower
Take a 200 MW facility. By the textbook, in a day it burns 4.8 mln kWh of electricity and evaporates 8,640 m³ of water.
Desalinating these 8,640 m³ of produced water in the ARBOK reactor takes 6,221 kWh a day — 0.13% of the data center’s energy use. Evaporation of the same volume will eat 864,000 to 2,160,000 kWh, that is 18–45%: a constant load of 36–90 MW. A difference of 139–347 times. And a membrane at 10–20% salinity is simply not applicable, in 2 passes or in 10.
The Arbok bonus is salt. At 10–20% salinity, the unit produces 860–1,730 t of dry salt every day. This is no longer waste but a commodity. Its price in the US on EWX terms (ex works, ex factory) is up to $100 per ton, that is $86,000–173,000 a day and $31–63 mln a year.
The water after the reactor contains no salts, does not clog the cooling system, and even cleans off scale deposited earlier. All bacteria and pathogens in it are killed, so it keeps for years without spoiling: for a cooling loop that means an end to biofilm and no biocides.
ARBOK Offers a Whole Line of Containerized Units
Not 1 unit but a whole line: all containerized, all without membranes and consumables, all on one physics of phase separation. ARBOK-BRINE handles brine of any strength, up to 35.5% salt, at the same energy: 200 t a day in a vertically installed 20-foot container that takes up just 8 m² of floor area. For those who have already installed osmosis, Arbok processes their brine into water and dry salt, and the plant gives 2.2 times more fresh water from the same intake. For the Permian Basin this is very relevant.
The Economics Favor the Oilman First
It is a debatable question. The oilmen themselves need water, they buy it on the side at $40 per m³, and it is as hard for them to find as for data centers. In essence, they are competitors. When the oilmen realize that Arbok cleans their brine, they will keep the cleaned water for themselves: they will not have to pay for injection or look for water, and the earthquakes will stop. That is good for the oilmen, but not a solution for data centers.
Well, let us believe in oilmen-philanthropists. Disposal of produced water in the Permian Basin — hauling, pipes, injection — costs a dollar or more per barrel. 8,640 m³ is about 54,000 barrels, that is about $54,000 a day and about $20 mln a year for one 200 MW data center. Not bad, but against what the oilmen themselves pay for clean water, it is a tiny figure.
In the US, the Permian Basin alone produces over 3 mln m³ of water a day: that is about $20 mln a day and $7 bln a year on hauling and injection. Worldwide, produced water is about 40 mln m³ a day, and everywhere today it is a cost item, not a product.
The salt that is injected into the formation together with the water today becomes a product worth $31–63 mln a year. Together with the savings on hauling and injection, that is $51–83 mln a year from one data center. Electricity costs about $750 a day (6,221 kWh at $0.12) — less than a data center spends on coffee for its staff.
And finally, a question the study never asks: what does a month of frozen construction cost, halted by the governor? For a facility worth billions of dollars, it is loan interest, broken contracts, departed customers. And a data center that takes on the Arbok process does not ask the city for water — it gets it from produced brine, solves the ecology and earthquake issues, and speaks to the regulator in a very different tone.
The Current Path Is Primitive, and Nature Pays for It
Personally, I am not against data centers. They are needed, and they will be built — all over the world, wherever there is land, cheap electricity, and demand, but not enough water. But the current way of solving the water problem is primitive and demands huge irreversible investment, while nature suffers. Drill one more well into the fresh aquifer, install one more osmosis unit (it is like using 2 condoms at the same time), inject the concentrate underground and cause an earthquake — and call it “sustainable development”.
The farmer whose well level is dropping pays. The city that restricts watering pays. The land that shakes from injection pays. And the data center itself pays, when it is refused a permit.
And to the data centers I will say it straight: do you need cooling or water? That is not the same thing! Arbok has developed a new type of vacuum evaporation for the cooling towers of nuclear plants, factories, and data centers: water goes round in a circle without being released into nature, and there is no need to take it from the authorities or the oilmen. Losses will always occur, but they are about 3–5%. Any governor will give you that volume!
The Industry Has Walked in One Circle for 50 Years
Either membranes or boiling. The membrane is made thinner, the pump more powerful, the heat exchanger longer, energy is taken from solar panels, and they shout on every corner that they have gone “green”. This does not solve a single problem. The best they have offered is to take water from the oilmen. That is debatable, and it can work only in Texas. And what about those places with no oilmen? What kind of “solution” is that?
The solution came at the junction of different sciences. As usual.
While Texas counts new metrics, scientists reinvent the wheel, oilmen keep shaking the ground with injection, data centers keep taking water from cities, and the governor keeps construction on pause. All 3 problems are solved by one unit from the Arbok Institute, installed right at the field. The oilman stops paying for disposal of produced water — he starts selling it. The data center gets cooling water that does not grow biofilm. The city gets its wells back. The region gets salt to sell and ground that no longer shakes.
Scientists ask which of the 2 desalination methods to choose for data centers. The answer is simple: the third.